OACETT Internationally Educated Professional Practice Exam IEPPE Question # 28 Topic 3 Discussion

OACETT Internationally Educated Professional Practice Exam IEPPE Question # 28 Topic 3 Discussion

IEPPE Exam Topic 3 Question 28 Discussion:
Question #: 28
Topic #: 3

You are a member of OACETT, a principal in XYZ Company and also a member of a city council. The city council approves appropriations for projects undertaken by the city. One such project is an energy conservation project with a large potential reduction in energy costs. XYZ Company has established a good reputation in the energy conservation field. XYZ Company has submitted a proposal to the city council to provide services for this project under consideration.

Which is the best analysis of Alternative G2?


A.

Alternative G2 is the most ethically acceptable. You would not be in a conflict of interest situation nor would you be betraying your company's confidential information.


B.

Alternative G2 would keep you out of any ethical trouble both with the client and with your employer.


C.

Alternative G2 is contractually and ethically correct especially in light of the conditions surrounding the offer.


D.

Alternative G2 is not ethically acceptable. While you would not jeopardize proprietary information belonging to your employer, you would jeopardize your relationship with the client by turning them down. This could in turn jeopardize your client’s relationship with your employer. This would not be fair to your employer.


Get Premium IEPPE Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.