Nutanix Certified Services Core Infrastructure Professional (NCS-Core 6.8) NCS-Core Question # 36 Topic 4 Discussion

Nutanix Certified Services Core Infrastructure Professional (NCS-Core 6.8) NCS-Core Question # 36 Topic 4 Discussion

NCS-Core Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

A customer has engaged a Nutanix consultant to deploy a cluster consisting of two NX-3460-G6 blocks. The consultant arrives at the customer site and fines the following:

* One rack with a total of 5U available

* Two ToR switches with 14 total available ports

* Dual PDUs with six available sockets

What will prevent the consultant from successfully installing the cluster?


A.

Insufficient sockets for power allocation.

Rack space may not be continuous.


B.

Insufficient rack space for block installation.

Insufficient sockets for power allocation.


C.

Insufficient network ports for communication.

Insufficient sockets for power allocation.


D.

Insufficient network ports for communication.

Insufficient sockets for power allocation.


E.

Insufficient network ports for communication.

Rack space may not be continuous.