NFPA Certified Water-Based Systems Professionals CWBSP Question # 21 Topic 2 Discussion

NFPA Certified Water-Based Systems Professionals CWBSP Question # 21 Topic 2 Discussion

CWBSP Exam Topic 2 Question 21 Discussion:
Question #: 21
Topic #: 2

Working plans are required to have the total system volume of the system for


A.

wet systems.


B.

open-head deluge systems.


C.

dry systems.


D.

antifreeze systems.


Get Premium CWBSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.