For a successful deployment of a switchless HA pair with two NetApp DS224C shelves in an already populated rack, it is crucial to verify:
Rack units: Ensure that there are enough rack units available to accommodate the new shelves and any associated equipment. Proper planning of space in the rack is essential for a neat and functional setup.
Power connections: Verify that there are sufficient and appropriately rated power connections available. Ensuring proper power distribution and redundancy is critical for the reliability and uptime of the storage system.