A crew of electricians is needed to run 1,000 feet of conduit, and the estimator determined that two electricians could complete the job in an eight-hour day. What is the required productivity rate per person for the conduit install?
Productivity rate = Total conduit / Total labor hours = 1000 feet / 16 hours = 62.5 feet per hour per person. (Fundamentals of Crew Leadership, Fourth Edition, NCCER, Section 4.4.1 Understanding Productivity Rates)