Microsoft Power BI Data Analyst PL-300 Question # 16 Topic 2 Discussion

Microsoft Power BI Data Analyst PL-300 Question # 16 Topic 2 Discussion

PL-300 Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

You have a Power BI report. The report contains visualizations that have interactions. You need to identify which visualizations take the longest to complete. What should you use?


A.

SQL Server Profiler


B.

Performance Analyzer in Power BI Desktop


C.

Query Diagnostics in Power BI


D.

Microsoft Edge DevTools


Get Premium PL-300 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.