Microsoft Dynamics 365 Supply Chain Management MB-330 Question # 17 Topic 2 Discussion

Microsoft Dynamics 365 Supply Chain Management MB-330 Question # 17 Topic 2 Discussion

MB-330 Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

A company uses Dynamics 365 Supply Chain Management. The company implements master planning.

The company reports delays in the supply chain that have resulted in late deliveries for products. You must simulate several broad delays across all products in the supply chain when calculating lead times. Daily planning for items must not be impacted.

You need to configure the system.

What should you configure?


A.

Planned orders


B.

Receipt margins


C.

Master plans


D.

Coverage groups


E.

Released products