AZ-400 Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

You have an approval process that contains a condition. The condition requires that releases be approved by a team leader before they are deployed.

You haw a pokey stating that approvals must occur within eight hours.

You discover that deployments only if the approvals take longer than two hours.

You need to ensure that the deployments only fail if the approvals take longer than hours.

Solution From Post -deployment conditions, you modify the Timeout setting for post-deployment approvals.

Does this meet the goal?


A.

Yes


B.

NO