Question #: 6
Topic #: 1

A fast-growing service provider is introducing separate roles of deployment manager and deployment practitioner. Which TWO activities is a deployment manager responsible for?

    Ensuring that deployment records are up-to-date and correct

    Prioritizing multiple deployments that require use of the same resources

    Ensuring deployment plans support other service management plans

    Capturing and verifying users’ opinions on deployments


A.

1 and 2


B.

2 and 3


C.

3 and 4


D.

1 and 4