ITIL 4 Foundation Exam ITIL-4-Foundation Question # 26 Topic 3 Discussion

ITIL 4 Foundation Exam ITIL-4-Foundation Question # 26 Topic 3 Discussion

ITIL-4-Foundation Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

What is a change schedule used for?


A.

To help plan emergency changes


B.

To help authorize standard changes


C.

To help assign a change authority


D.

To help manage normal changes