ISTQB-CTFL Exam Topic 1 Question 9 Discussion:
Question #: 9
Topic #: 1

Which of the following activities are part of test planning?

I) Setting the entry and exit criteria

II) Determining the validity of bug reports

III) Determining the number of resources required

IV) Determining the expected result for test cases


A.

I. IV


B.

I. III


C.

I, III, IV


D.

I, II, IV