A calculator application is being developed. The third sprint has been planned to add functionality to the calculator to allow scientific calculations. Which TWO examples below represent activities that would likely be managed on an agile task board for the third sprint?

I) A task to design the features planned for the next sprint.

ii) A task to run an acceptance test for a user story.

iii) A task to automate regression tests.

iv) A task to participate in training in preparation for the fourth sprint.

v) A task to produce a daily progress report for the agile team members.

SELECT ONE OPTION


A.

iv, v


B.

i. iv


C.

i. v


D.

ii, iii