Question #: 7
Topic #: 1

You have been assigned to a project that has a very tight schedule.In fact, given your first analysis you do not think the planned test execution can be completed within the schedule There is no time allowed for defectfixing or for repeating tests.Regression testing has been left out of the planning entirely There is no time to develop test automation.The team has agreed that this Is not the way to run a project, yet they are stuck with the current schedule

Given this information what is the best way to proceed with the testing to try to meet the deadline with the best outcome1?


A.

Review the personnel plan and get more resources onto the test team


B.

Continue with the current plan but highlight to the project manager that either the deadline will be missed or the testing will not be done


C.

Develop a test automation plan so that automation can be started now


D.

Conduct a quality risk analysis and prioritize the testing based on risk so the highestrisk items are tested first