A test status report should:


A.

specify the impediments to carrying out the planned test activities in the reporting period and the corresponding solutions put in place to remove them


B.

be produced as part of test completion activities and report unmitigated product risks to support the decision whether or not to release the product


C.

always be based on the same template within an organization, as its structure and contents should not be affected by the audience to which the report is presented


D.

specify the lines of communication between testing, other lifecycle activities, and within the organization that were chosen at the outset of the test project