Which of the following Is an example of tasks most associated with the test design activity?


A.

Test data, derived from production data, is developed for use during testing


B.

The project manager updates the project schedule as key test tasks are completed


C.

The Identification of test execution and test automation tools


D.

Every day, the tester notes the status of his/her test cases in preparation for daily reports