Which of the following risks represents the highest level of risk to the project?


A.

Likelihood of failure = 1%, potential cost of impact = $1m.


B.

Likelihood of failure = 10%, potential cost of impact = $500,000.


C.

Likelihood of failure = 20%, potential cost of impact = $150,000.


D.

Likelihood of failure = 5%, potential cost of impact = $500,000.