iSQI ISTQB Certified Tester Foundation Level (Syllabus 2018) CTFL_Syll2018 Question # 27 Topic 3 Discussion

iSQI ISTQB Certified Tester Foundation Level (Syllabus 2018) CTFL_Syll2018 Question # 27 Topic 3 Discussion

CTFL_Syll2018 Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

Which of the following metrics could be used to monitor progress along with test preparation and execution? [K1]


A.

The total number of tests planned


B.

The total number of requirements to be tested


C.

The failure rate in testing already completed


D.

The number of testers used for test execution so far