Question #: 5
Topic #: 1

Choose the VALID description of the ramp-up concept.

SELECT ONE OPTION


A.

Stage of reaching the stationary state.


B.

Stage of finishing the test.


C.

Stage of exit from a stationary state by increasing the number of concurrent users.


D.

Technique in which the load on the system is increased to a certain value in the shortest possible time.