Question #: 20
Topic #: 3

In a sprint planning, the product owner presents a user story written on a card. The team starts having a discussion with the product owner to get an understanding on how the software should work.

The user story written on the card is:

"As a customer, I want to subscribe to the mailing list so that I can receive the latest deal in an email."

By applying the 3C concept, which ONE of the following statements is CORRECT?


A.

Conversation should include the acceptance criteria discussion.


B.

The card should contain requirements not the user story.


C.

Product owner has written a user story and confirmation is not needed.


D.

The conversation is not required and the team should start developing.