Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
Create an estimate based on the function point analysis technique and test point analysis
Create an estimate based on the complexity of the code
Create an estimate based on the credentials of the successful bidder
Create an estimate based on a percentage of the development effort