Given is the following defect removal chart reported at the end of system testing - showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are classified as critical. All tests have been executed.

CTFL-001 Question 48

Based on the chart above, what is the most appropriate next test phase? 1 credit


A.

Acceptance testing to verify the business process


B.

Acceptance testing to verify operational requirements


C.

Requirements testing as part of testing regulatory compliance


D.

Another system test cycle to verify defect resolution