CTFL-001 Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

Testing should be stopped when:


A.

All the planned tests have been run


B.

Time has run out


C.

All faults have been fixed correctly


D.

Both A and C


E.

It depends on the risks for the system being tested