DEF, Inc. is finalizing a contract to have its head office refurbished. Within its budget of $1.2 million there is a general risk fund of $30,000. The building is old, and the electrical wiring drawings do not appear up to date. The total project bid from Supplier X is $1 million. This includes a fee of $20,000 for updating electrical wiring drawings and the contractors' risk fund of $100,000, half of which is for building-related issues, and half of which is for electrical issues.
DEF decides to assume the risk of electrical issues. What is the contract price paid to Supplier X?