A supply manager issues a purchase order to buy battery packs over the next three years. The battery packs will be used for multiple applications within the company. The first shipment is delivered in accordance with the quality standards and the delivery schedule outlined in the purchase order. Shortly thereafter, the supply manager is informed by an end user that the batteries from a second shipment are missing a component and are of no value. The supply manager immediately notifies the supplier it is in material breach and terminates the purchase order. The supply manager then informs the user departments of this decision.
Which of the following BEST describes what the supply manager did wrong (if anything) in this scenario?
Submit