A supply manager seeks bids on a new piece of capital equipment. The equipment is budgeted at $115,000. Three suppliers send in bids of $110,000, $114,000 and 5135,000. After receiving the bids, additional negotiations with the low bidder result in a final cost of $105,000. In this situation, what should the baseline value be for calculating cost avoidance?


A.

$114,000


B.

$135,000


C.

$110,000


D.

$115,000