ISM Supply Management Core Exam CORE Question # 64 Topic 7 Discussion

ISM Supply Management Core Exam CORE Question # 64 Topic 7 Discussion

CORE Exam Topic 7 Question 64 Discussion:
Question #: 64
Topic #: 7

A manufacturing plant employs an enterprise resource planning (ERP) system. The supply management staff find the data provided by this system to be incomplete or incorrect. Which of the following should the supply management staff do FIRST In order to obtain more useful information?


A.

Analyze the spend categories and establish cost baselines


B.

Obtain extensions on reporting deadlines and track current transactions as examples


C.

Retrain supply management employees in the proper use of the ERP system


D.

Request approvals to implement a more effective ERP system