BCD Inc. is in the early stages of selecting a new procure to pay (P2P) system, which is expected to add efficiencies and reduce transaction costs. Which of the following is the BEST way for supply management to participate in the selection of this system?


A.

Consult with key suppliers to learn their requirements for integration


B.

Construct a detailed list of transaction types and estimated processing times


C.

Ensure that BCD's IT department understands the top suppliers' requirements for integration


D.

Conduct a survey to learn what transactions are regarded as cumbersome