Question #: 20
Topic #: 3

A supply manager for FGH, Inc. places a purchase order for 10 widgets with a supplier. The supplier ships 10 widgets and invoices for 10 widgets, and the end user receives 10 widgets. However, the procure to pay system shows receipt of 8 widgets. The supplier demands to be paid the full amount. Responsibility for resolving this issue will fall to FGH's


A.

receiving department


B.

senior management


C.

accounts payable department


D.

supply manager