Question #: 2
Topic #: 1

Which of the following sections of the SEMP template defines the project constraints, to include constraints on funding, personnel, facilities, manufacturing capability and capacity, critical resources, and other constraints


A.

Section 3.1.5


B.

Section 3.1.8


C.

Section 3.1.9


D.

Section 3.1.7