Isaca Certified in Risk and Information Systems Control CRISC Question # 62 Topic 7 Discussion

Isaca Certified in Risk and Information Systems Control CRISC Question # 62 Topic 7 Discussion

CRISC Exam Topic 7 Question 62 Discussion:
Question #: 62
Topic #: 7

When an organization's business continuity plan (BCP) states that it cannot afford to lose more than three hours of a critical application's data, the three hours is considered the application’s:


A.

Maximum tolerable outage (MTO).


B.

Recovery point objective (RPO).


C.

Mean time to restore (MTTR).


D.

Recovery time objective (RTO).