When an organization's business continuity plan (BCP) states that it cannot afford to lose more than three hours of a critical application's data, the three hours is considered the application’s:
TheRecovery Point Objective (RPO)specifies the maximum tolerable period in which data might be lost due to an incident. In this case, the organization is indicating that it cannot afford to lose more than three hours of data, defining its RPO.