Question #: 591
Topic #: 60

A risk action plan has been changed during the risk mitigation effort. Which of the following is MOST important for the risk practitioner to verify?


A.

Impact of the change on inherent risk


B.

Approval for the change by the risk owner


C.

Business rationale for the change


D.

Risk to the mitigation effort due to the change