Which of the following is a risk practitioner's BEST recommendation to help reduce IT risk associated with scheduling overruns when starting a new application development project?


A.

Implement a tool to track the development team's deliverables.


B.

Review the software development life cycle.


C.

Involve the development team in planning.


D.

Assign more developers to the project team.