The GREATEST benefit of including low-probability, high-impact events in a risk assessment is the ability to:


A.

develop a comprehensive risk mitigation strategy


B.

develop understandable and realistic risk scenarios


C.

identify root causes for relevant events


D.

perform an aggregated cost-benefit analysis