Question #: 476
Topic #: 48

A control owner has completed a year-long project To strengthen existing controls. It is MOST important for the risk practitioner to:


A.

update the risk register to reflect the correct level of residual risk.


B.

ensure risk monitoring for the project is initiated.


C.

conduct and document a business impact analysis (BIA).


D.

verify cost-benefit of the new controls being implemented.