Isaca Certified in Risk and Information Systems Control CRISC Question # 468 Topic 47 Discussion
CRISC Exam Topic 47 Question 468 Discussion:
Question #: 468
Topic #: 47
When an organization ' s business continuity plan (BCP) states that it cannot afford to lose more than three hours of a critical application ' s data, the three hours is considered the application’s:
TheRecovery Point Objective (RPO)specifies the maximum tolerable period in which data might be lost due to an incident. In this case, the organization is indicating that it cannot afford to lose more than three hours of data, defining its RPO.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.