Isaca Certified in Risk and Information Systems Control CRISC Question # 463 Topic 47 Discussion

Isaca Certified in Risk and Information Systems Control CRISC Question # 463 Topic 47 Discussion

CRISC Exam Topic 47 Question 463 Discussion:
Question #: 463
Topic #: 47

Which organization is implementing a project to automate the purchasing process, including the modification of approval controls. Which of the following tasks is lie responsibility of the risk practitioner*?


A.

Verify that existing controls continue to properly mitigate defined risk


B.

Test approval process controls once the project is completed


C.

Update the existing controls for changes in approval processes from this project


D.

Perform a gap analysis of the impacted control processes