Question #: 414
Topic #: 42

Which of the following is the PRIMARY reason that risk management is important in project management?


A.

It helps identify and mitigate potential issues that could derail projects.


B.

It helps to ensure project acceptance by end users.


C.

It reduces the risk associated with potential project scope creep.


D.

It facilitates agreement and collaboration on project goals among stakeholders.