Isaca Certified in Risk and Information Systems Control CRISC Question # 33 Topic 4 Discussion

Isaca Certified in Risk and Information Systems Control CRISC Question # 33 Topic 4 Discussion

CRISC Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

During a risk treatment plan review, a risk practitioner finds the approved risk action plan has not been completed However, there were other risk mitigation actions implemented. Which of the fallowing is the BEST course of action?


A.

Review the cost-benefit of mitigating controls


B.

Mark the risk status as unresolved within the risk register


C.

Verify the sufficiency of mitigating controls with the risk owner


D.

Update the risk register with implemented mitigating actions


Get Premium CRISC Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.