Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Isaca Certified in Risk and Information Systems Control CRISC Question # 299 Topic 30 Discussion

Isaca Certified in Risk and Information Systems Control CRISC Question # 299 Topic 30 Discussion

CRISC Exam Topic 30 Question 299 Discussion:
Question #: 299
Topic #: 30

A risk action plan has been changed during the risk mitigation effort. Which of the following is MOST important for the risk practitioner to verify?


A.

Impact of the change on inherent risk


B.

Approval for the change by the risk owner


C.

Business rationale for the change


D.

Risk to the mitigation effort due to the change


Get Premium CRISC Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.