Question #: 248
Topic #: 25

Which of the following is the BEST metric to demonstrate the effectiveness of an organization's patch management process?


A.

Average time to implement patches after vendor release


B.

Number of patches tested prior to deployment


C.

Increase in the frequency of patches deployed into production


D.

Percent of patches implemented within established timeframe