Question #: 191
Topic #: 20

Deviation from a mitigation action plan's completion date should be determined by which of the following?


A.

Change management as determined by a change control board


B.

Benchmarking analysis with similar completed projects


C.

Project governance criteria as determined by the project office


D.

The risk owner as determined by risk management processes