CRISC Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

The MOST important reason to monitor key risk indicators (KRIs) is to help management:


A.

identity early risk transfer strategies.


B.

lessen the impact of realized risk.


C.

analyze the chain of risk events.


D.

identify the root cause of risk events.