Question #: 149
Topic #: 15

The PRIMARY reason for tracking the status of risk mitigation plans is to ensure:


A.

the proposed controls are implemented as scheduled.


B.

security controls are tested prior to implementation.


C.

compliance with corporate policies.


D.

the risk response strategy has been decided.