Which of the following should be scheduled for completion FIRST when prioritizing improvement initiatives?
Initiatives that are easiest to achieve and will garner business benefits
Initiatives that are the least expensive in order to lower risk due to failure
Initiatives with the lowest cost regardless of expected business value
Submit