COBIT-Design-and-Implementation Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

What is the role of the change enablement component in the continual improvement life cycle approach of EGIT implementation?


A.

To address behavioral and cultural aspects of the EGIT improvement or implementation


B.

To manage the changes in the enterprise's organizational structures resulting from the EGIT improvement or implementation


C.

To identify what needs to be done in terms of solutions for day-to-day practices as part of the EGIT improvement or implementation


D.

When reviewing the success of the EGIT initiative, identify further actions to improve the governance system