Question #: 179
Topic #: 18

An organization requires that business-critical applications be recovered within 30 minutes in the event of a disaster. Which of the following metrics should be in the business continuity plan (BCP) to manage this requirement?


A.

Maximum tolerable downtime (MTD)


B.

Service level agreement (SLA)


C.

Recovery point objective (RPO)


D.

Recovery time objective (RTO)