Isaca Certified Information Systems Auditor CISA Question # 431 Topic 44 Discussion
CISA Exam Topic 44 Question 431 Discussion:
Question #: 431
Topic #: 44
An IS auditor is reviewing an IT project and finds that an earned value analysis (EVA) is not regularly performed as part of project status reporting. Which of the following is the GREATEST risk resulting from this situation?
A.
Resources might not be assigned and prioritized in a timely manner.
B.
Time and budget overruns might not be identified in a timely manner.
C.
The project might not be compliant with project management standards.
D.
Business requirements may not be properly benchmarked.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit