CISA Exam Topic 43 Question 423 Discussion:
Question #: 423
Topic #: 43

Which of the following is the PRIMARY reason for an IS auditor to conduct post-implementation reviews?


A.

To determine whether project objectives in the business case have been achieved


B.

To ensure key stakeholder sign-off has been obtained


C.

To align project objectives with business needs


D.

To document lessons learned to improve future project delivery