CISA Exam Topic 41 Question 401 Discussion:
Question #: 401
Topic #: 41

Which of the following should be the FIRST step in a data migration project?


A.

Reviewing decisions on how business processes should be conducted in the new system


B.

Completing data cleanup in the current database to eliminate inconsistencies


C.

Understanding the new system ' s data structure


D.

Creating data conversion scripts