CISA Exam Topic 40 Question 395 Discussion:
Question #: 395
Topic #: 40

An organization has developed mature risk management practices that are followed across all departments What is the MOST effective way for the audit team to leverage this risk management maturity?


A.

Implementing risk responses on management ' s behalf


B.

Integrating the risk register for audit planning purposes


C.

Providing assurances to management regarding risk


D.

Facilitating audit risk identification and evaluation workshops


Get Premium CISA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.